Leeds Bradford Airport’s ambitions to expand are under scrutiny as a public inquiry examines proposed increases in passenger capacity and changes to night-time flight regulations. The inquiry, initiated in March 2025, addresses appeals following enforcement actions by Leeds City Council regarding night-time flight limits.
Read the full report at:
https://cockpitking.com/leeds-bradford-airport-expansion-public-enquiry/?amp=1
Thanks Cockpitking. Clearly a lot of work there and much appreciated.
Just a couple of points to note in response:
The 2019 planning consent did not include the refurbishment of the existing terminal, only the construction of the extension. The refurbishment due to start around now, was added as part of LBA Regen, and doesn't need planning consent as the works are internal.
LBA does not have BA flights to London Heathrow. They were terminated during Covid. That route has not been served since apart from a brief and hopeless attempt by Flybe mk2.
Jet2 operate precisely zero A321NEO routes out of LBA, nor are any scheduled for the foreseeable future. All flights are by 737 800 and 300 series.
Flights in the past on longer haul routes were not all charters, as suggested, and not all made fuel stops due to runway restrictions. PIA operated non stop to Islamabad on A310 equipment. So did Shaheen Airways before them. They were scheduled services.
Further back Wardair flights to Toronto did a split load, picking up at BHX, but operated direct inbound. On one occasion, a DC10, replacing the usual 747 operated both ways non stop. Britannia also operated non stop on some occasions to Bridgetown , so it can be done. LBA say the runway can now handle aircraft up to Boeing 787 and Airbus A350 size but this is yet to be tested, in part because the terminal cannot handle that size of aircraft (yet).
LBA deny they have exceeded the night movement limit other than the first year post lockdown. Leeds City Council took no action that year and so far have taken no action relating to last year either..They continue to enforce a planning approval from 1994, despite that approval indicating that updated NOTAMs (which update aircraft types permitted to operate at night) should be taken into account. If the intention was not to use updated NOTAMs, reflecting new technology , then it wouldn't be referenced in the planning approval.
The new stands are to be built at a rate of 2 per year for 5 years, 10 in total. All will be on what currently is grassed area around the existing apron.
Hope that helps